March 2012 |
Interior work progresses, rental lease-up starts |
February 2012 |
Interior work progresses |
January 2012 |
Interior work progresses |
December 2011 |
Weatherization completed, brick work continues, interior work started |
November 2011 |
Exterior, paving, roofing completed, exterior brick work continues |
October 2011 |
Framing, roofing continues, window frames installed, |
September 2011 |
Framing continues upward |
August 2011 |
Basement and first floor framing underway |
July 2011 |
Foundations finished, lower walls and steel beams started |
June 2011 |
Site prep and foundation construction |
May 2011 |
Site excavation and clean-up continues |
April 2011 |
Site excavation and clean-up |
March 2011 |
Existing building demolition and clean-up |
Nov.2010 - February 2011 |
Site preparation, scrap and asbestos removal for demolition |
October 2010 |
Financing Completed and Closed, Groundbreaking Celebrated |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|